Luton Ambulance Station
16 week project, Luton
- Gutter Refurbishment
- Asbestos Removal
- Commercial Roofing / Cladding
Asbestos strip and re-sheet of roof and new wall cladding installed.
16 week project, Luton
Asbestos strip and re-sheet of roof and new wall cladding installed.
14 week project, Wales
Full removal of the aged existing roof, replacement of compromised purlins and installation of Tata Steel Trisomet® composite panels. Delivered to the Tata Steel Platinum Plus specification system.
12 week project, Haverhill
Installation of a new 230mm built-up roof system over the existing asbestos roof and safely remove the old asbestos parapet wall, installing a new cladded parapet.
7 week project, Swindon
Over-clad of existing metal roof.
6 week project, Mildenhall
Garland spec asbestos strip and composite sheet installation
12 week project, Staines-upon-Thames
CRE renovated the building before a new lease by ALDI and Lok'n Store.
22 week project, St. Neots
This large-scale 5000 m² warehouse refurbishment project based in Saint Neots is the perfect example of what CRE specialise in.
14 week project, London
Wenzels approached us with a clear and concise request: “We would like to install solar panels on our roof.”
35 week project, Norfolk
A very interesting and challenging project transforming former cattle feed barns to Three, high end residential units.
7 week project, Cambridge
We were tasked with designing, supplying and fitting the “outer shell” which was to be 3” black plastisol coated sinusoidal sheeting.